La Costa Town Square
Carlsbad, CA

Project Schedule

    • City of Carlsbad release La Costa Town Square project for grading – December 2012
    • Mobilization and site grading of La Costa Town Square – January 2013
    • Residential development under construction – June 2013
    • Grading, retaining walls, and underground utilities completed – December 2013
    • Building construction begins – December 2013
    • Construction completion – March 2014
    • Pre-Opening Event – November 7, 2014
    • Grand Opening expected – Spring 2015